New Local Plan

Search representations

Results for Environment Agency search

New search New search

Comment

New Local Plan

6. How best do you think we can improve the transport system serving Southend

Representation ID: 3938

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

The C2C operated rail service from Southend Central to Fenchurch Street crosses the Hadleigh Marshes which is an area a risk of flooding from the Thames Estuary and is identified in the Action Plan for Zone 6 of the Thames Estuary 2100 Plan. The TE2100 Plan has recommended a P3 policy for the future management of the tidal defences that protect the Hadleigh Marshes. Policy P3 advocates continuing with existing or alternative actions to manage flood risk. This means that we will continue to maintain flood defences at their current height, accepting that the likelihood and/or consequences of a flood will increase because of sea level rise. This policy therefore has potential impacts for the long term sustainability of the railway line as the chance of overtopping of the tidal defences will increase over time.
Our Thames Estuary Asset Management 2100 (TEAM2100) are near to completing an appraisal to help inform a future management strategy for the tidal defences at Hadleigh Marshes. We are therefore keen to develop the management strategy and to commence dialogue to develop a long term programme with Southend Borough Council, Castle Point Borough Council, C2C Rail Operator, Network Rail and landowners as partners to better understand resilience opportunities for the rail transport infrastructure. The strategy that we develop must ensure that long term impacts of climate change on the C2C service and Network Rail infrastructure are understood and is built into local plans for infrastructure improvement and for flood warning.

Comment

New Local Plan

10. How best do we plan for the future impacts of climate change

Representation ID: 3939

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

Support the inclusion of the renewal and replacement of sea defences as one of the challenges illustrated in Figure 7 of the Issues and Options document.
Should develop planning policies for development of new or renewed sea defences and make clear requirements for contributions towards infrastructure on sites that come forward (from s106 or CIL). Local planning policies for the development of new or renewed sea defences would add weight to the recommendations of the TE2100 Plan and could set a framework for protecting land that is important for future flood defences (NPPF para 157b), and for making clear requirements for contributions towards infrastructure on sites that come forward that will benefit from those defences, or for integration of new developments with defences.
Policy P3 of TE2100 Plan (to continue to maintain flood defences at current height) will have long term implications for C2C line with chance of overtopping tidal defences increasing over time.

Comment

New Local Plan

10. How best do we plan for the future impacts of climate change

Representation ID: 3940

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

Would expect to see a section in the Local Plan looking at wastewater infrastructure and treatment, including:
• Sewerage networks – to ensure there is sufficient volumetric capacity in the existing sewerage networks in each of the areas where development is planned. If no capacity is currently available, then provisions need to be in place ahead of the occupation of dwellings.
• Water Recycling Centres (WRC) – to highlight which WRC within the district are proposed to receive additional flows from planned development. A thorough assessment of existing capacity and future flows against the current discharge permit should be made (this is usually done via the WCS). Any WRC predicted to exceed its permitted Dry Weather Flow will require a new discharge permit to accommodate the additional growth – this may contain potential tighter permit limits which could provide a constraint on development.
• Demonstrate that adequate foul drainage infrastructure can be provided in a timely manner ahead of occupation of new properties – both for sewerage network and WRCs
Demonstrate that the proposed development can be delivered without causing a breach of environmental legislation (should not cause a deterioration in the receiving rivers/waterbodies)

Comment

New Local Plan

12. How best do you think the Local Plan can be effectively delivered in the face of limited resources

Representation ID: 3941

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

Would expect to see a section in the Local Plan looking at wastewater infrastructure and treatment, including:
• Sewerage networks – to ensure there is sufficient volumetric capacity in the existing sewerage networks in each of the areas where development is planned. If no capacity is currently available, then provisions need to be in place ahead of the occupation of dwellings.
• Water Recycling Centres (WRC) – to highlight which WRC within the district are proposed to receive additional flows from planned development. A thorough assessment of existing capacity and future flows against the current discharge permit should be made (this is usually done via the WCS). Any WRC predicted to exceed its permitted Dry Weather Flow will require a new discharge permit to accommodate the additional growth – this may contain potential tighter permit limits which could provide a constraint on development.
• Demonstrate that adequate foul drainage infrastructure can be provided in a timely manner ahead of occupation of new properties – both for sewerage network and WRCs
• Demonstrate that the proposed development can be delivered without causing a breach of environmental legislation (should not cause a deterioration in the receiving rivers/waterbodies)

Comment

New Local Plan

10. How best do we plan for the future impacts of climate change

Representation ID: 3942

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

Acknowledge challenges of surface water flooding – will need to work together as respective Flood Management Authorities with responsibilities under the Flood & Water Management Act 2010.
Sustainable drainage systems should be promoted as they offer the opportunity to enhance the environment by providing blue infrastructure and can increase water quality, as well as providing drainage to developments.
Detailed requirements for SuDs are provided – also please refer to the SuDS Manual (CIRIA C753, 2015), the Susdrain website (http://www.susdrain.org/) and the draft National Standards for SuDS (Defra, 2015) for more information.

Comment

New Local Plan

10. How best do we plan for the future impacts of climate change

Representation ID: 3943

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

Need to add Thames and Anglian River Basin Management Plans to evidence base.

Comment

New Local Plan

10. How best do we plan for the future impacts of climate change

Representation ID: 3944

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

Water cycle study (WCS) 2010 – The Council’s WCS dates from 2010 - would expect to see a WCS referenced in the plan and summary of findings/recommendations linking to how development will be dealt with sustainably.
The section on climate change does not mention the effect this may have on water supply. Water resources should be protected for people and the environment.
We would like to see consideration of water supply for all new developments. We recommend an assessment regarding availability of water supply for further development and water saving measures. Development should be phased to ensure water supply demands are met.

Comment

New Local Plan

9. How best do we protect and enhance our environment in the face of increasing growth and development pressures

Representation ID: 3945

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

We feel that green infrastructure should be given a more prominent place in this part of the plan. All development should be required to incorporate meaningful green infrastructure. Features that could be incorporated into developments include swales, ponds, reed beds and wildflower rich grasslands. Incorporating features such as green roofs and walls can be particularly effective measures providing urban habitats, increasing energy efficiency for buildings and attenuation of rain water.

Comment

New Local Plan

1.4 How should Southend develop in the future in seeking to deliver 18,000 - 24,000 new homes and 10,000 - 12,000 new jobs, please select from one of the options stating your reasoning.

Representation ID: 3946

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

Encourage the use of brownfield sites and contamination issues should be considered - Further information can found in the groundwater protection documentation at https://www.gov.uk/government/collections/groundwater-protection

Comment

New Local Plan

9. How best do we protect and enhance our environment in the face of increasing growth and development pressures

Representation ID: 3947

Received: 26/03/2019

Respondent: Environment Agency

Representation Summary:

Encourage the use of brownfield sites and contamination issues should be considered - Further information can found in the groundwater protection documentation at https://www.gov.uk/government/collections/groundwater-protection